Wednesday, July 8, 2015

Solar power; sunny side down



Does the German experience aimed at promoting renewables such as solar and wind to replace fossil fuel capacity and nuclear energy, have any relevance in India’s case?


On March 20, the day a major solar eclipse was predicted, electricity grid managers in Germany weathered three extremely nervous hours — the duration of the eclipse. At 38.5 gigawatts of capacity (1 GW is equal to 1,000MW or mega watt), Germany has nearly half of Europe’s total of 89 gigawatts of solar capacity and accounts for more solar PV installed than any other nation. For a nation that, in theory, has solar capacity that is enough to meet half of its peak demand, a solar eclipse posed a litmus test for grid operators in terms of how they manage the sudden drop in solar output. Especially since the region’s last notable eclipse was way back in 2003, after which Germany’s solar power output has expanded sharply.

The March 20 eclipse, which cut off 65 to 80 per cent of incoming sunlight across parts of Europe, tested the engineers at Germany’s four big electricity network operating companies, who had to make sure that the resultant fluctuation in solar power production would not destabilise the grid. The German grid managed to tide over the challenge by drawing on alternative power sources, including coal, gas, biogas, nuclear and pumped storage hydroelectric energy, alongside a commensurate cut in demand from industry including four aluminum plants.

GERMANY’S ENERGIEWENDE EXPERIENCE

Does the German experience with ‘Energiewende’, its flagship programme aimed at promoting renewables such as solar and wind to replace fossil fuel capacity and nuclear energy, have any relevance in India’s case? Two weeks back, the NDA government announced plans to raise the country’s solar power generation capacity addition target five times to 100 GW by 2022, which will entail an investment of around Rs 6 lakh crore.

The revised target, up from 20 GW earlier, will principally comprise 40 GW (solar) rooftop and 60 GW through large and medium scale grid connected solar power projects. To put the target in perspective, a solar capacity of 100 GW is about 40 per cent of the country’s current installed capacity. While going solar is, in some ways, a growing fad among government seeking to make an emphatic green statement, there might be some relevant concerns as well.

Going back to Germany’s case, there are fundamental question marks that countries with large solar generation base are faced with. Germany’s residential electricity cost is about $0.34/kWh, one of the highest globally. An estimated $0.07/kWh reportedly goes directly to subsidising renewables, which is higher than the wholesale electricity price in Europe. In India, the focus on solar power has been largely limited to the last seven years. In 2009, the the Jawaharlal Nehru National Solar Mission (JNNSM) was launched with a target for grid-connected solar projects set at 20,000 MW by 2022.



In the last two-three years, the sector has seen renewed activity, with the installed solar capacity increasing rapidly from just 18 MW to about 3,800 MW during 2010-15. Encouragingly, the price of solar energy has come down significantly from around Rs 17.90 per unit in 2010 to under Rs 7 per unit, thereby reducing the need of viability grant funding or VGF per MW of solar power. With technology advancement and market competition, this green power sources is expected to achieve grid parity by 2017-18. It is in this context that the Cabinet gave its approval for the setting up of over 2,000 MW of grid-connected solar photo voltaic power projects on a Build, Own and Operate (BOO) basis with VGF funding under the second phase of the JNNSM.

COST BREAK-UP

The fine print of the project shows that the government has estimated the cost of a solar project at a ballpark estimate of Rs 6 cr/MW — including VGF at Rs 1cr/MW for the open category and Rs 1.31 crore/MW for the Domestic Content Requirement or DCR category (where domestic manufacturing is mandatory). A pre-defined tariff of Rs 5.43 per kWh has been provided for projects under the scheme for the first year, with an escalation of 5 paisa per kWh each year till the tariff reaches the level of Rs 6.43 per kWh. This would take 21 years and the tariff, thereafter, would remain capped at Rs 6.43 per kWh. The levelized tariff would be
Rs 5.79 per kWh.

Out of 2,000 MW, 250 MW will be developed with mandatory condition of solar PV cells and modules made in India. This will be called the DCR category and remaining 1,750 MW will be in open category.

The total investment in setting up 100 GW of solar capacity is estimated at around Rs 6,00,000 cr, excluding the cost of transmission, which would be in the range of Rs 1.5 cr/MW for land-based (non-rooftop) solar plants to be connected with the main grid. It is not clear out of 100GW, how much capacity will be mandated through the DCR category.

A breakdown of the numbers, though, poses somes questions. For instance, the land required for 60,000MW of solar plants at about 5 acres per MW comes to a whopping 3 lakh acres. Add to this the cost of inter-state and intra-state transmission at Rs 1.5 crore per MW comes to Rs 90,000 crore. Since the solar plants will be located in barren and remote areas away from load centres such as Kutch, Barmer, Jaisalmer and Ladakh, and voltage compensation devices such as reactors and static VAR compensators would also be required, the cost of transmission escalate further and the wheeling cost would be even higher because the energy produced by a solar plant in a year is about 25 per cent that of a thermal plant of the same capacity and 50 per cent of a hydro plant of same capacity.

STANDBY CHARGES and GRID SECURITY

Then there is the issue of standby charges for thermal plants, precisely because the actual output of a solar plant is not so smooth. Solar power varies over the day depending on time of the day, location and weather, and needs conventional power as back up until viable mass energy storage devices are invented. So, the electricity distribution companies or discoms needs to pay the standby charges of coal-based generation.

If one were to add the transmission charges and losses, and standby charges to the levelised solar generation cost of Rs 5.79, experts contend that the landed cost would go up to about Rs 9.00 per unit, excluding the cost of capital subsidy and tax benefits. Now the impact of the 100 GW of solar power plan on the financial health of the debt-ridden discoms could be catastrophic, and question marks remain on how the domestic consumers pay these higher electricity prices.

There is also the issue of grid security. In order to deal with the variability of renewable generation, forecasts are crucial for resource adequacy during operation and grid security. In order to absorb 100 GW of solar power in a day, the output of conventional generation would have to be varied in tandem to match the 100 GW, failing which other grid security could be endangered. This, most industry players contend, is a daunting task. All developed countries in the world including China have Automatic Generation Controls, something that India lacks. That makes the challenge of operating the grid even more daunting.

MANUFACTURING IMPETUS AND EMPLOYMENT

Germany may top in terms of solar capacity, but the Chinese solar plants are, by far, the cheapest in the world and the Chinese are the biggest manufacturer of PV panels. Going by the current trend, industry estimates peg that 80 per cent of the Rs 6 lakh crore solar business
may be bagged by China. So, despite the ‘Make in India’ push, more jobs will be created in China that in India from our solar push.


No comments:

Post a Comment

About Me

My photo
Thrissur, Kerala, India
Those who have power to change things don't bother to;and those who bother don't have the power to do so .................but I think It is a very thin line that divides the two and I am walking on that.Well is pure human nature to think that "I am the best and my ideas unquestionable"...it is human EGO and sometimes it is very important for survival of the fittest and too much of it may attract trouble.Well here you decide where do I stand.I say what I feel.

Followers

Blog Archive